One & Six Year
Road Improvement Plan
Dakota County, Nebraska

February, 1997

horizontal rule

Item # 1

Project # C-22(118)

Year 97-98

Description:

Relocate existing road around farmstead and gravel, beginning .1 mile E of the W1/4 corner of Sec. 20, T29N, R7E, then NE 1/4 mile. Kramper

County Funds $10,000

horizontal rule

Item # 2

Project # C-22(133)

Year 97-98

Description:

Dakota City West 0.18 miles NDOR # @TP-3967(2)

Federal Share (80%) $36,502
Local Share (20% by Dakota City) 9,126
Total $45,628

horizontal rule

Item # 3

Project # C-22(139)

Year 97-98

Description:

Replace existing culvert with a new culvert. Between Sections 27 & 28, T27N, R8E Homer Southwest.

County Share $100,000

horizontal rule

Item # 4

Project # C-22(140)

Year 97-98

Description:

Remove existing bridge and replace with dam. Bridge No. C002200905P Sec. 8, T7E, R27N Herman Simmons
NRD Project

NRD Funds 60% of $75,000 $45,000
County Share 40% + $41,000 $71,000
Total Project Cost $116,000

horizontal rule

Item # 5

Project # C-22(145)

Year 97-98

Description:

Bomag, reshape and armor coat surfacing Omaha Ave., Fiddler Creek Road to Wigle Creek road.

County Funds $32,000

horizontal rule

Item # 6

Project # C-22(146)

Year 97-98

Description:

Bomag, reshape and armor coat surfacing, Unnamed Street between Atokad and Freeway Mobil Homes, Atokad Drive to Gateway Drive.

County Funds $15,000

horizontal rule

Item # 7

Project # C-22(147)

Year 97-98

Description:

Build new backwall and wings on Bridge No. 01010P Hogh Bridge. In Sec 30 T29N R7E

County Funds $22,000

horizontal rule

Item # 8

Project # C-22(148)

Year 97-98

Description:

Regrade 260th Street, Perry Ave. to "O" Ave. 1.5 miles

County Funds $35,000

horizontal rule

Item # 9

Project # C-22(149)

Year 97-98

Description:

Regrade, grub trees and grade backslope on minimum maintenance road. 110th Street, N-12 West 1 miles.

County Funds $10,000

horizontal rule

Item # 10

Project # C-22(109)

Year 97-98

Description:

Remove and replace existing bridge No 00505P with CMP, grade and gravel, .3 miles North of the south 1/4 corner of Section 13, T28N, R6E. Galvin

County Funds $10,000

horizontal rule

Item # 11

Project # C-22(141)

Year 97-98

Description:

Remove and replace Bridge No. C002230315P. Sec. 23, T29N, R6E Twohig Bridge

County Funds $10,000

horizontal rule

Item # 12

Project # C-22(72)
(Metric)

Year 98-99

Description:

Remove existing Bridge No. 01105P and replace with new structure, 1.7 miles south and 1.5 miles west of Hubbard, crossing Pigeon Creek. Sec. 33, T28N, R7E-Stork

HUBBARD SW - BRO-7022(6)

Federal Share 80% $89,994
State Share 10% $11,249
County Share 10%
(Soft Match Credit)
$11,249
TOTAL PROJECT COST $112,492

horizontal rule

Item # 13

Project # C-22(142)

Year 97-98

Description:

Regrade existing road and provide adequate drainage, beginning at the intersection of "l" Avenue and 120th Street. Between Secs. 11-12, T29N, R7E, then North 1-1/2 miles

County Share $20,000

horizontal rule

Item # 14

Project # C-22(74)A
Metric

Year 98-99

Description:

Construct 8" by 24' Portland Cement concrete pavement. South 2 miles of Hubbard-Jackson Road STPE-3925(1) Hubbard Northeast

FAS Funds 80% $360,000
County Funds 20% $90,000
TOTAL PROJECT COSTS $450,000

horizontal rule

Item # 15

Project # C-22(119)

Year 99-2000

Description:

Remove and replace existing bridge with CMP near the North 1/4 corner of Sec. 13, T29N, R6E (Not listed on bridge inventory) Frant O'Neill

County Funds $25,000

horizontal rule

Item # 16

Project Number C-22(74)B
Metric

Year 99-2000

Description:

Construct 8" by 24' Portland Cement concrete pavement and one drainage structure. North 2 miles of Jackson-Hubbard Road Jackson Southwest, STPE-3925 (2)

FAS Funds 80% $360,000
County Funds 20% $90,000
TOTAL PROJECT COST $450,000

horizontal rule

Item # 17

Project # C-22(122)

Year 99-2000

Description:

Remove and replace existing Bridge No. 02515P Approx. .2 miles west of the center of Sec. 14, T27N, R8E. 1st south of Homer on asphalt.

County Funds $160,000

horizontal rule

Item # 18

Project # C-22(150)

Year 99-2000

Description:

Remove and replace existing Bridge No. 20715, 3 miles Southwest of Willis. Between Sec. 1, T28N, R6E and Sec. 6, T28N, R7E

Federal Funds 80% $256,000
State Funds 10% $32,000
County Funds 10%
(Soft Match Credit)
$32,000
TOTAL PROJECT COSTS $320,000

horizontal rule

Item # 19

Project # C-22(123)
Metric

Year 2000-01

Description:

Homer South, 0.20 miles South of Homer. Sec. 23, T27N, R8E -- Bridge No. 02510P

Homer South -- BRO-7022(11)

Federal Funds 80% $162,780
State Funds 10% $20,348
County Funds 10%
(Soft Match Credit)
$20,348
TOTAL PROJECT COST $203,476

horizontal rule

Item # 20

Project # C-22(124)

Year 2002-03

Description:

New construction and R-O-W purchase for a new by pass between South Sioux City and Dakota City, beginning at the Northeast corner of the Southwest 1/4 Northeast 1/4 of section 34 T29N, R9E. River Front Road.

County Funds $200,000

horizontal rule

PROJECTS COMPLETED DURING FY 1996

Item # 1

Project # C-22(112)

Description:

Homer, Northeast Sec. 7, T27N, R9E- Bridge No 03105 R-O_W has been acquired. Letting 1-18-96

BRO-7022(12)

Federal Funds 80% $237.925.44
State Funds 10% $29,740.68
County Funds 10%
(Soft Match Credit)
$29,740.68
TOTAL PROJECT COST $297,406.80

horizontal rule

Item # 2

Project # C-22(135)

Description:

Replace Bridge No. 01710P and road project. Kenesaw Road Sec. 13, T27N, R7E (Corkscrew)

County Funds $48,000.00

horizontal rule

Item # 3

Project # C-22 (143)

Description:

Bomag, reshape, and armor coat surfacing, Lake Avenue, Tomkins Drive to Old Sawmill road (Tomkins Addition)

County Funds $20,000.00

horizontal rule

Item # 4

Project # C-22 (144)

Description:

Bomag, reshape, and armor coat surfacing, 9th Street from the Southeast corner of Sec. 17, T89N, R47W, West 1320' (Trailer Court to A-1 Salvage)

County Funds $20,000.00

horizontal rule

The following project is to be dropped
from the One and Six Year Plan

Project # C-22(108)

Description:

Remove and replace Bridge No. 000320 at the Northwest corner of Sec. 11, T28N, R6E. Adams.

County Funds $125,000

horizontal rule

Road Committee members are James Huggenberger and Jack Bobier of the

 